Task Time Estimator
A PERT estimate from optimistic, likely and pessimistic times.
Runs in your browser. Nothing is uploaded — your input is processed on this device and discarded when you close the tab.
Task Time Estimator
How to use this tool
- Type the three estimates in the same unit (hours, days or minutes) — optimistic, most likely, then pessimistic.
- Press Generate. The tool shows the PERT expected time, the standard deviation and the expected range.
- Use Load sample for a 2 / 4 / 12 hour task, or Clear to start again.
Worked example
For optimistic 2 hours, most likely 4 hours and pessimistic 12 hours, the expected time is (2 + 4 x 4 + 12) / 6 = 5.00 hours, the standard deviation is (12 - 2) / 6 = 1.67 hours, so the likely range is 3.33 to 6.67 hours.
What this tool does not do / Limits
This is a planning estimate, not a promise: it assumes the three estimates are honest and in the same unit, and it requires optimistic at most most likely at most pessimistic. It does not account for dependencies, waiting time or other tasks.
Frequently asked questions
What is the PERT formula?
The expected time is (optimistic + 4 x most likely + pessimistic) / 6, which weights the most likely case four times as heavily as either extreme. The standard deviation is (pessimistic - optimistic) / 6.
Why is the range expected plus or minus one standard deviation?
That range covers the most common outcomes under the PERT model. Roughly two-thirds of similar tasks finish inside it, so plan buffers beyond it for anything deadline-critical.
Related tools
CSV Cleaning Studio
Remove duplicates, fix missing values, standardise dates and export a clean CSV. Your file never leaves your device.
LiveChart Builder
Build charts from CSV data with aggregation, sorting and accessible colour palettes. Export as PNG or SVG.
LiveLength Converter
Convert lengths between metric and imperial units and see the full table of equivalents.
Live